Project Details
Project Scope
This project resulted in the road widening of Willow Dr, which included removing 1,500 feet of existing curbing to make way for a new bike lane. We then formed and poured 1,500 feet of new curbing to match the updated road alignment. As part of the improvements, we installed a new bus stop and completed a mill and overlay of the existing street to ensure a smooth, durable surface.
Challenges
- Tight Deadline: All work had to be completed by July 31 to allow an on-time student move-in to the new apartment building. Diligent scheduling and extended work hours ensured timely completion without compromising quality.
- Maintaining Traffic Flow: Willow Drive had to remain open throughout the project. Strategic planning enabled multiple safe and efficient lane shifts to keep traffic moving with minimal disruption.
Outcome
The project was completed on schedule, ensuring the planned move-in date was met while maintaining continuous traffic flow and prioritizing pedestrian safety during the project.
Let's Build Stronger Foundations Together
At Lloyd Grading & Utilities, Inc., we’ve provided full-service site preparation since 2006. We’re committed to delivering infrastructure solutions that stand the test of time.
Contact us today to discuss your project needs and experience the difference of working with a local, family-owned industry leader.
Contact Us